That's right. Highland and Ellis (near the softball complex) is getting a signal so expect closures and delays. Here's what we can expect...

According to the City of Bozeman road report details:

  • Work is underway to install a signal at the intersection of Highland and Ellis.
  • This project will involve partial closures and detours and could cause delays in traffic movement.
  • PLEASE CHECK THE LINK ABOVE FOR DETAILED MAPS.
  • East Leg of Ellis CLOSED 9/24/19 for approximately 7 days
  • South leg of Highland CLOSED week of Sept 30  for 8 days
  • Expect minor closures of corners of intersections to be ongoing until project is complete
  • Detour signs will be in place.
  • Drivers traveling in the area should use other routes when possible or allow extra time to get to your destination.
  • Crews will be working Monday through Friday and will have roads reopened, whenever possible, during the weekend.
  • Schedules are weather dependent. The project is expected to be completed in late November.

Contact Information for project questions:
Sanderson Stewart
406-922-4306

Highland Ellis Closure map - COB